Work sampling in garment industry studies is a way to find out how people and machines spend their time by making many quick, random observations instead of timing every second with a stopwatch. At each observation the observer records only what the person or machine is doing at that moment, such as sewing, waiting for work, fixing a problem or idle. After enough observations, the share of observations in each category gives a good estimate of the share of time spent in that category. It is a simple tool, and it is very useful for questions like “how much of the day is the line really sewing?”
This guide explains what work sampling is, how it differs from a time study, where it is used in a garment factory, how to plan and run a study, how to work out the number of observations needed, a worked example and the mistakes to avoid. It is written for industrial engineers, line supervisors, production managers and students.

What work sampling is
Work sampling, also called activity sampling or the ratio delay method, is based on a simple idea from statistics. If you look at a person at many random moments, the proportion of times you find them doing a certain activity will be close to the proportion of time they spend on that activity. A person who is found waiting for work in 20 out of 100 random observations spends roughly 20 percent of the time waiting.
You do not need a stopwatch, and you do not need to stay at one machine. One observer can walk the floor, make a quick note and move on. That is why work sampling can cover a whole line, a department or many machines in one study.
Work sampling and time study
Both belong to work measurement, but they answer different questions. For the full list of techniques, the guide to work measurement techniques in the garment factory is a good place to start.
| Point | Time study | Work sampling |
|---|---|---|
| What it measures | The time of each element of a repeated job | The share of time spent on each activity |
| Best for | Short, repeated operations, such as sewing a collar | Mixed or irregular work, such as helpers, mechanics, supervisors and whole lines |
| Tool | Stopwatch, video | Tally sheet and a schedule of random times |
| Observer effort | Continuous at one place | Short visits over a long period |
| Main result | Cycle time, standard time | Percent of time working, idle or delayed |
| Disruption to workers | Higher, as the observer stands nearby | Lower, as visits are brief |
Use time study to set the time of a repeated sewing operation, and use work sampling to understand how the day is used. They support each other. For the time study side, the guide to cycle time in garment manufacturing is a good place to start.
Where it is used in a garment factory
- Operator utilisation. How much of the shift are operators actually sewing, compared with waiting, walking or doing other things?
- Machine utilisation. How much of the time are machines running, and how much are they idle, broken or waiting for work?
- Idle time and delay causes. What share of lost time comes from waiting for cut parts, waiting for a mechanic, waiting for approval or searching for materials? The guide to idle time in a garment factory explains the details.
- Indirect labour. What do helpers, material handlers, mechanics, quality checkers and supervisors do with their time?
- Allowances. How much time do operators really need for rest, personal needs and small delays? This helps set realistic allowances. The guide to how to calculate standard allowed minutes is a useful companion here.
- Staffing. How many helpers or checkers does a line really need?
- Before and after studies. A method or layout change can be judged by comparing the share of working time before and after.
- Checking line balance. If some operators are idle much of the time, the line may be unbalanced. The guide to line balancing in the garment industry covers this in more detail.
How work sampling works
- Decide what you want to find out, and list the categories of activity.
- Decide who or what is to be observed.
- Plan random times for the observations.
- At each time, walk to the place and record the activity of each person or machine at that exact moment.
- Keep going until you have enough observations.
- Count the observations in each category, and work out the percentages.
- Check that the sample is large enough for the accuracy you need.
- Report the results and act on them.
Steps in detail
Step 1: define the purpose
State the question clearly. For example: “What percentage of working time is lost to waiting for work on lines 4 to 6?” A clear question sets the categories and the study length.
Step 2: choose the activity categories
Keep the categories few, clear and different from each other. For a sewing line, a useful list might be:
| Category | What it covers |
|---|---|
| Working | Sewing, handling, trimming, checking the piece |
| Waiting for work | No bundle at the machine |
| Machine problem | Waiting for a mechanic, thread break repair, machine stopped |
| Quality or rework | Fixing defects, waiting for a check |
| Setup | Changing thread, needle, folder or attachment |
| Personal | Rest, drinking water, toilet |
| Other delay | Looking for materials, instructions, talking about work |
| Absent from workstation | Not at the machine for other reasons |
Write a short definition for each, so all observers record in the same way. If a category is unclear, observers will argue over it, and the results will not be trusted.
Step 3: decide the group and the period
Choose the operators or machines to be observed, and the days of the study. Cover a normal mix of days and shifts. Do not choose only a Monday morning or only the last day of the month, since these may not be typical. A study often runs for a few days to a few weeks.
Step 4: plan random observation times
The observation times must be random, not regular. If you always walk the line at 10:00 and 14:00, workers will learn the pattern and the data will be biased. There are several ways to get random times:
- Use a random number table or a spreadsheet function to pick times within the shift.
- Divide the shift into short blocks and choose one random minute in each block.
- Use a random order of lines or sections for each round.
Keep the times secret from the people being observed, and keep the walk the same each round, so the observation is quick and at the instant of arrival.
Step 5: make the observations
At each planned time, walk the route and record what each person or machine is doing at the moment you see them. Record what is happening, not what you think ought to be happening. Do not wait to see how the activity ends. Do not adjust the result because you know the person.
A simple tally sheet works well. List the categories as columns and the observation rounds as rows, or use a tablet with a form.
Step 6: calculate the results
For each category, the percentage is:
Percentage = number of observations in the category divided by the total number of observations, times 100
For example, if 108 of 480 observations show “waiting for work”, that category is 22.5 percent of observed time.
Step 7: check that the sample is large enough
A small number of observations gives results that can change a lot from one study to the next. A larger sample gives more reliable results. The next section shows how to work out the number of observations needed.
Step 8: report and act
Present the percentages in a clear table or chart, with the number of observations. Show the biggest categories of loss first. Then use the findings to plan improvements, and repeat the study afterward to check the result.
How many observations are needed
The number depends on how accurate you need the result to be, and on the share of time in the category you care about. A common formula for a 95 percent confidence level is:
n = (1.96 squared times p times (1 minus p)) divided by E squared
Where:
- n is the number of observations needed.
- p is the expected share of the activity, as a fraction. Use an estimate from a short trial study.
- E is the accuracy wanted, as a fraction of total observations, for example 0.05 for plus or minus 5 percentage points.
- 1.96 is the value for 95 percent confidence.
Some books use 2 in place of 1.96, so the result may differ by a small amount.
A worked example with assumed figures
A planner wants to know what share of the time on a sewing line is lost waiting for work. A short trial of 100 random observations finds 20 in the category, so p is 0.20. The planner wants the final estimate to be correct within plus or minus 5 percentage points at 95 percent confidence, so E is 0.05.
n = (1.96 squared times 0.20 times 0.80) divided by 0.05 squared n = (3.8416 times 0.16) divided by 0.0025 n = 0.6147 divided by 0.0025 n = about 246 observations
The planner rounds up and decides to take about 250 observations or more. Because the line has 30 operators, each round of the line gives 30 observations, so about 9 rounds are enough. In practice the planner takes more rounds to cover different days and shifts.
After the full study of 480 observations, 108 show the operator waiting for work. The share is 108 divided by 480, which is 22.5 percent. The interval at 95 percent confidence is plus or minus 1.96 times the square root of (0.225 times 0.775 divided by 480), which is about plus or minus 3.7 percentage points. So the true share is most likely between about 18.8 and 26.2 percent.
On a 480 minute shift, 22.5 percent is 108 minutes per operator per day spent waiting for work. That is a large loss, and the next step is to find out why, for example by looking at cutting supply, bundle flow and balance. The figures here are assumed for illustration, so use your own data.
If you need the result to be more accurate, such as plus or minus 2 percentage points, the required number of observations rises sharply, so decide how accurate you really need to be before you start.
Using work sampling to set a standard time
Work sampling can also help to set a standard time for work that does not repeat in a short cycle, such as material handling or packing. The method uses the total output over the study period, the share of time spent working and a rating of the operator’s pace.
Time per unit = (total time observed times share of working time times rating) divided by units produced
An allowance is then added to get the standard time. Because rating needs judgement, this use of work sampling requires a trained observer. Many factories use work sampling mainly for utilisation and delay studies, and use time study or standard data for sewing operations. For how standard times are recorded for operations, the guide to the operation bulletin in garments is a good place to start.
Tips for a good study
- Tell people what you are doing. Explain that the aim is to improve the system and not to blame individuals. This builds trust and gives honest results.
- Train the observers. Make sure all observers understand the categories and record in the same way. Do a trial round together.
- Keep it random. Use a real random schedule, and avoid habits.
- Record at the instant of arrival. What the person is doing at that second is the observation.
- Do not use the data to punish. If it is used to blame, people will change their behaviour and the next study will not show the truth.
- Cover enough days. Include different days, shifts and stages of the order.
- Use a pilot. Run a short trial to test the categories and to estimate p.
- Keep records. Save the tally sheets with the date, line and style.
- Combine with other data. Compare the findings with production records, downtime logs and quality records.
Common mistakes
| Mistake | Why it is a problem | How to avoid it |
|---|---|---|
| Fixed observation times | Workers learn the pattern, and results are biased | Use a random schedule |
| Too few observations | Results are unreliable | Work out the sample size first |
| Unclear categories | Observers record differently | Write clear definitions and test them |
| Too many categories | Slows the study and confuses observers | Keep the list short |
| Observing only one day or shift | Not typical of normal work | Spread observations over days and shifts |
| Recording what should happen | Biased data | Record what you see at the instant |
| Observer influences behaviour | People work differently when watched | Explain the study and keep visits brief |
| Using results to blame | Future studies are distorted | Use the data to improve the system |
| Ignoring the cause | Numbers alone do not fix the problem | Follow with a root cause study |
What to do with the results
The numbers show where time is lost. The next step is to find out why and to act.
- Waiting for work. Look at cutting supply, bundle flow, line balance and material handling. The guide to the bottleneck identification in the sewing line goes deeper on this.
- Machine problems. Look at maintenance and mechanic response. The guides to TPM in garment factory sewing machines and the sewing machine maintenance schedule explain the details.
- Rework and quality. Look at first time quality and inspection. The guide to rework in the garment factory is a useful companion here.
- Setup and changeover. Look at the changeover process. The guide to style changeover time reduction covers this in more detail.
- Method. Study the working method itself. The guide to method study in the garment industry goes deeper on this.
- Overall picture. Combine the findings with the wastes of lean. The guide to the seven wastes of lean in a sewing factory explains the details.
- Machine effectiveness. Link the results to the guide on OEE in garment manufacturing.
Then repeat the study after the change. A drop in waiting time from, say, 22 percent to a lower figure shows that the fix worked. Also see the guide to productivity vs production efficiency formulas for the connection between utilisation and efficiency.
Digital tools
Some factories now use tablets, simple forms or tracking systems to record sampling data and to calculate results automatically. Others use cameras and sensors that record machine states. These tools can reduce the work of recording, but the principles stay the same. For related methods, the guide to real time production tracking on the sewing floor is a good place to start.
Final thoughts
Work sampling in garment industry settings is a fast, low cost way to see how time is really used. By making many short, random observations and recording what each person or machine is doing at that instant, you can estimate the share of time spent working, waiting, repairing or idle. It works well for whole lines, indirect staff and irregular work, where a stopwatch study is hard.
To use it well, define clear categories, plan random times, work out the number of observations from the accuracy you need, observe at the instant of arrival and explain the purpose to the people on the floor. In the worked example, 22.5 percent of the shift was lost to waiting for work, which is about 108 minutes in a 480 minute day. Numbers like that point to the next question: why, and what can be fixed first.
Frequently asked questions
It is a method of making many random, instant observations of people or machines to estimate the share of time spent on each activity, such as working, waiting or machine repair.
A time study measures the time of each element of a repeated job with a stopwatch. Work sampling measures the share of time spent on different activities, using random observations.
It depends on the accuracy wanted and the share of the activity. A common formula for 95 percent confidence is n equals 1.96 squared times p times (1 minus p) divided by E squared.
If times follow a pattern, workers may change their behaviour at those times, and the data will be biased. Random times give a fair picture.
It can for irregular or non repetitive work, using the share of working time and a rating of pace. For repeated sewing operations, time study or standard data is more common.
Keep a short list, such as working, waiting for work, machine problem, quality or rework, setup, personal time and other delays. Write a clear definition for each.
Long enough to reach the required number of observations and to cover different days and shifts. Many studies run for several days to a few weeks.