Throughput Time in Garment Industry: Formula and Reduction

Throughput time in garment industry work is the total time a garment, or a lot of garments, spends inside the factory between the start of production and the moment it is finished. It counts every hour, whether the work is being done or the lot is just sitting and waiting. In most sewing factories the waiting is the bigger part, and that is the reason this number is worth measuring.

throughput time in garment industry

Many factories track output per hour and efficiency, and both are useful. Neither one tells you how long a style takes to get through the building. Throughput time does. A line can show good efficiency and still hold the same cut lot for ten days, with bundles piled between operations, stock tied up in the floor and problems found late. This guide explains what throughput time means, how it differs from lead time and cycle time, what it is made of, how to calculate it with a worked example, why it gets long and how to bring it down. It is written for industrial engineers, production managers, planners and merchandisers.

What throughput time means

Throughput time is the elapsed time from the moment materials are released to production to the moment the finished goods leave the last process. In a garment factory that is usually the time from the start of cutting to the end of packing. Some factories start the clock at fabric issue, and others stop it at the carton being closed or sent to the shipping area. The exact start and stop points matter less than using the same ones every time.

You can measure it for one piece, for one bundle, for a cut lot or for a whole order. For a lot, the clock starts when the first part is cut and stops when the last piece is packed, or you can track the first and last piece separately. Always write down which one you used.

Throughput time covers two kinds of time. One is working time, when the garment is actually being cut, sewn, pressed or packed. The other is waiting time, when the garment is in a queue, in transit, in a hold area or on a rework table. In many factories the second kind is far larger than the first.

Throughput time, lead time, cycle time and takt time

These terms are used in different ways in different books and factories. Some sources treat throughput time and lead time as the same thing, and some treat throughput time and cycle time as the same thing. So the first job is to agree on your own meaning and write it down. The table shows one common way to separate them.

TermWhat it measuresExample
Throughput timeTime a lot spends inside the production flow, from start to finish, working and waitingCutting start to packing end for a 1,200 piece lot
Lead timeTime from order confirmation to delivery, including sourcing, approvals, production and shippingPO date to ex factory date
Cycle timeTime for one operation or one unit at a station, or the time between finished unitsTime to sew one collar
Takt timeThe pace the customer demand needs, from available time divided by pieces requiredOne piece every 20 seconds

Throughput time sits inside lead time. Lead time also includes fabric sourcing, lab dips, sample approvals, waiting for trims and shipping. See lead time in garment manufacturing for the full picture of an order, and takt time in garment manufacturing for the demand pace.

A useful way to remember it: takt time is the pace you should run at, cycle time is how long one step takes, and throughput time is how long the product actually stays in the system.

What makes up throughput time

For a lot moving through the factory, throughput time is the sum of four parts.

  • Process time. The time the lot is being worked on, such as spreading and cutting, sewing, pressing or packing. This is the only part that adds value in the buyer’s eyes.
  • Inspection time. The time spent checking, such as fabric checks, inline checks, end of line checks and final inspection. It is needed, but it does not change the garment.
  • Move time. The time spent carrying or transporting the lot between sections, floors, buildings or outside processes such as washing, printing and embroidery.
  • Queue time. The time the lot waits before the next step can start. It waits for a free machine, for the next operator, for trims, for an approval, for a trolley or for the line to be ready.

So the basic formula is simple:

Throughput time = process time + inspection time + move time + queue time

When you add these up for a real lot, the queue is often the largest part. It does not show on any machine log, which is why it stays hidden.

Where the time goes in a garment factory

It helps to walk through the flow in order and ask where the lot waits.

  • Fabric store and relaxation. Fabric waits for inspection, for relaxation (especially knits), for approval or for the cut order. This time often sits outside the cutting start, but it is part of the full flow if you count from fabric issue.
  • Cutting. The lot waits for spreading, for the marker, for the cutting table and for numbering and checking. See cutting department in a garment factory.
  • Bundling and supply. Cut parts wait to be bundled, ticketed and sent to the line, and then wait again until the line has room for them. See bundle ticket and bundling in a garment factory.
  • Sewing. Bundles wait between operations. The slower the operation and the bigger the bundle, the longer the queue. Rework adds loops.
  • Outside processes. Washing, printing, embroidery or dyeing add transit, waiting for a slot and waiting for results.
  • Finishing. Garments wait for thread trimming, pressing, spot cleaning, final checking and tagging.
  • Packing. Garments wait for the carton, the packing list and the final audit. See garment packing methods.

A simple stage by stage record of the lot like this is the base of a value stream map. See value stream mapping in a garment factory.

The formulas

There are three formulas that are used most often.

1. From time stamps

Throughput time = finish time minus start time

If the first part of a lot was cut at 8:00 on Monday and the last carton was closed at 16:00 on Friday, the throughput time is the working time between those two moments. Count only the hours the factory works, or count calendar hours. Use one way and stay with it.

2. From the four parts

Throughput time = process time + inspection time + move time + queue time

This lets you see which part is large and where to act.

3. From work in process and output (Little’s law)

Throughput time = work in process (WIP) ÷ output rate

This is a general rule for any flow. If you know how many pieces are in the system and how many leave it per day, the average time a piece stays is WIP divided by output. See what is WIP and how to calculate it. It assumes the flow is fairly steady, so treat it as an average.

There is also a ratio that shows how much of the time is useful work:

Value added ratio = process time ÷ throughput time × 100

Some books call this manufacturing cycle efficiency. A low figure means the lot spends most of its life waiting.

A worked example

The figures below are assumed to show the method. Use your own records on the floor.

Part 1: a lot from the start of cutting to the end of packing

A lot of 1,200 T-shirts is tracked through five stages. All times are working hours for the whole lot, and one working day is counted as 8 hours.

StageProcessInspectionMoveQueueTotal hours
Cutting5.00.50.58.014.0
Bundling and supply to sewing1.50.01.016.018.5
Sewing8.01.02.024.035.0
Finishing6.01.51.010.018.5
Packing3.01.00.56.511.0
Total23.54.05.064.597.0
  • Throughput time = 23.5 + 4.0 + 5.0 + 64.5 = 97.0 working hours, or 97.0 ÷ 8 = about 12.1 working days.
  • Value added ratio = 23.5 ÷ 97.0 × 100 = 24.2 percent.
  • Queue share = 64.5 ÷ 97.0 × 100 = 66.5 percent.

Of the 97 hours, only 23.5 are spent working on the lot. Two thirds of the time is waiting. The largest single wait is in sewing (24.0 hours), followed by bundling and supply (16.0 hours).

What happens if the waiting is cut? Suppose the factory cuts the bundle size, feeds the line only when it has room and balances the first operations. It removes 12 hours of queue from sewing and 12 hours from bundling and supply, 24 hours in all.

  • New throughput time = 97.0 − 24.0 = 73.0 working hours, about 9.1 working days.
  • New value added ratio = 23.5 ÷ 73.0 × 100 = 32.2 percent.

The same work gets done, and the lot leaves about three working days earlier. Nobody had to sew faster.

Part 2: the same idea with Little’s law on a sewing section

Assume a sewing section has 3,600 pieces of WIP on the floor and sends out 900 finished pieces a day.

  • Throughput time = 3,600 ÷ 900 = 4.0 days.

If the section caps its WIP at 1,800 pieces and still sends out 900 pieces a day, the throughput time is 1,800 ÷ 900 = 2.0 days. The output is unchanged and the pieces spend half as long in the section. In real life, output may change when WIP is cut, so check it after the change.

Why throughput time matters

  • Delivery. The shorter the time in the factory, the more room there is to absorb a delay before the ship date. It also helps when a buyer changes the order.
  • Cash. Fabric, trims and labour are tied up in every piece that sits on the floor. Less WIP means less money stuck in the building.
  • Quality. When a lot spends days in the factory, a defect made in the first operations may not be seen until the lot reaches the end. A short flow finds problems while the cause is still fresh. See DHU in a garment factory.
  • Flexibility. A factory with a short throughput time can change a style or a colour with less stock in the way.
  • Space and handling. Large piles of WIP need space and more handling, which brings damage, dirt and lost bundles.
  • Planning accuracy. If you know the real throughput time, you can plan cutting dates to match sewing needs, not guess them.

Why throughput time gets long

  • Big lots and bundles. A big lot cannot move on until the whole lot is done, so every piece waits for the others.
  • Cutting far ahead of sewing. Cutting finishes early and the parts wait in the store or on the line floor. This looks like good progress but adds pure waiting.
  • Poor line balance and bottlenecks. Work piles up in front of the slowest operation. See line balancing in the garment industry and bottleneck identification in the sewing line.
  • Missing material. A lot stops because trims, thread, labels or interlining are not at the line.
  • Rework loops. Defective pieces go back, wait for repair and come back again. See rework in a garment factory.
  • Slow approvals and inspections. The lot waits for first piece approval, a quality decision or a buyer comment.
  • Style changeover. The line stops while the next style is set up. See style changeover time reduction.
  • Outside processes. Washing, printing and embroidery add transit time and waiting for a slot.
  • Poor layout and long moves. Sections that are far apart or on different floors add move time.
  • Machine breakdowns and absence. A line that loses machines or operators holds its lots.
  • Idle time. Waiting operators are the other side of waiting work. See idle time in a garment factory.

How to measure it on the floor

You need a start time and a finish time for each lot, and ideally time stamps at each stage.

  1. Choose the start and stop points. For example, first cut to carton closed. Write them down.
  2. Stamp the lot at each stage. Use the bundle ticket, a route card or a tag, and record the time the lot enters and leaves each section.
  3. Record the reason for waits. Material, machine, approval, rework, transport or no operator.
  4. Calculate by stage. The gap between leaving one stage and entering the next is queue plus move time.
  5. Add up the four parts. Process, inspection, move and queue.
  6. Use WIP counts as a cross check. Count pieces on the floor at a fixed time each day and divide by daily output. If the two answers are far apart, one of your records is wrong.
  7. Track it each week by style. One lot is a sample. A trend shows what really changes.

Some factories use scanning or tracking systems to get these time stamps. See real time production tracking on the sewing floor. A simple paper route card works too, as long as people fill it in.

How to reduce throughput time

Most of the gain comes from cutting queue time, not from making people work faster.

  1. Use smaller lots and bundles. The lot can move on sooner, and problems appear earlier. Choose a size that the line can handle without too much ticket handling.
  2. Cut to the sewing plan. Cut what the line needs for the next days, not weeks ahead. See cut order plan in a garment factory.
  3. Limit WIP. Set a maximum number of bundles or pieces between operations or sections, and stop feeding when the limit is reached. A pull signal, such as a card or a board, helps. See kanban board in garments manufacturing.
  4. Balance the line and fix the bottleneck first. Improving the slowest operation shortens the wait for everything behind it.
  5. Have all materials ready before the style starts. Check trims, thread, labels and packing items before the first cut.
  6. Reduce rework at the source. Fewer defects means fewer loops.
  7. Speed up approvals. Set a time limit and name the person who decides.
  8. Shorten the moves. Place sections in flow order and use trolleys or conveyors that suit the work.
  9. Plan outside processes. Book slots for washing, printing and embroidery in advance and agree on turnaround.
  10. Prepare for changeover. Set up the next style while the current style is still running.
  11. Consider a production system that carries less WIP. Progressive bundle systems usually hold more WIP than unit production or modular systems, though each has its place. See progressive bundle, unit production and modular systems.
  12. Find the real causes. Use a stage by stage map and the waiting reasons you recorded, and work on the biggest cause first. See seven wastes in a lean sewing factory.

Change one thing at a time where you can, so you can see what worked.

Setting a target and following up

There is no single good throughput time for every factory. It depends on the product, the order size, the layout, the production system and the outside processes. So set a target for each product type, based on your own baseline. A reasonable method:

Share the figure with the planning, cutting, sewing and finishing teams, because the waits are often created between the sections.

Common mistakes

  • Mixing up the terms. Comparing a lead time figure with a throughput time figure gives wrong conclusions.
  • Changing the start and stop points. Then the trend means nothing.
  • Only counting working time. The waiting part is the point.
  • Using efficiency as the only measure. A line can have good efficiency and still hold stock for days.
  • Cutting WIP without fixing the cause. Stopping the feed without balancing the line can just leave operators idle.
  • Using one lot as the answer. One lot may be unusual, so check several.
  • Ignoring outside processes. Washing, printing and embroidery often hold the longest waits.
  • Not telling the people who feed and finish the line. The best gains come from sections working to the same pace.

Final thoughts

Throughput time in garment industry work is the time a lot spends in the factory from the start of cutting to the end of packing, including all the waiting. It is the sum of process, inspection, move and queue time, and in many factories the queue is the largest part. Little’s law gives a quick cross check: WIP divided by daily output.

Measure it for a few lots, split it by stage and write down the reason for each wait. Then cut the biggest queue first, using smaller lots, a WIP limit, a balanced line, ready materials and cutting that follows the sewing plan. The factory gains faster delivery, less money tied up on the floor and problems found earlier, often without anyone having to sew faster.

Frequently asked questions

What is throughput time in the garment industry?

It is the total time a garment lot spends in the factory from the start of production, usually cutting, to the end, usually packing. It includes working time and all the waiting, moving and checking time.

How do you calculate throughput time?

Add process time, inspection time, move time and queue time for the lot. You can also subtract the start time from the finish time, or divide the work in process by the daily output.

What is the difference between throughput time and lead time?

Lead time runs from order confirmation to delivery and includes sourcing, approvals and shipping. Throughput time covers only the time inside the production flow. Some books use the two words for the same thing, so define them in your factory.

What is the difference between throughput time and cycle time?

Cycle time is the time for one operation or one unit at a station, or the time between finished units. Throughput time is the total time a unit or lot spends in the whole process.

How can I reduce throughput time?

Cut queue time first. Use smaller lots and bundles, limit WIP, balance the line, fix the bottleneck, have materials ready, cut to the sewing plan, reduce rework and speed up approvals.

What is a good throughput time for a garment factory?

There is no single figure that suits every factory, because products, order sizes, layouts and production systems differ. Measure your own baseline by product type, find the biggest wait and bring it down step by step.

How does work in process affect throughput time?

More WIP means a longer stay for each piece. With Little’s law, throughput time equals WIP divided by output rate, so halving WIP at the same output halves the time.

Throughput Time in Garment Industry: Formula and Reduction

Leave a Reply

Scroll to top

Discover more from ORDNUR

Subscribe now to keep reading and get access to the full archive.

Continue reading